Cummins Highway Construction Update: September 2025

September 1, 2025 - September 5, 2025

Construction activity will be temporarily paused on Monday, 9/1 (Labor Day) and from Thursday 9/4 to Tuesday, 9/9

Install curb at roundabout

Install curb between Bismarck Street and Woodhaven Street

Begin installing curb between Corman Street and Itasca StreetContinue pouring cement for driveways between Wood/Harvard and Itasca

September 8, 2025 - September 12, 2025

Install curb between Ridlon Road and Rugby Road

Continue pouring cement for driveways between Itasca Street and Woodhaven Street

Begin paving bike lane from Itasca Street to Woodhaven Street

September 15, 2025 - September 19, 2025

Install curb between Ridlon Road and Rugby Road

Begin paving bike lane from Itasca Street to Woodhaven Street

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share us

on your social networks:
AGPs

Get the latest news on this topic.

SIGN UP FOR FREE TODAY

No Thanks

By signing to this email alert, you
agree to our Terms & Conditions